HSHS Renovations & Academic Wing Addition – Update
Henry-Senachwine High School renovations and construction on the new academic wing addition have continued over the past few weeks. The following progress has been made:
• Electrical rough-ins
• Installation of masonry walls
• Installation of steel joists and deck
• Caulking joints in precast walls
• Preparation and pouring of concrete floors
• Plumbing rough-ins in restroom areas
• Preparation and pouring of concrete for storm shelter and topping slab
• Installation of staircase
• Installation of roof over storm shelter area
• Installation of brick veneer
The District will provide progress updates on the high school academic wing addition and renovation work on its website at www.hscud5.org, under tab ‘Master Facility Planning”. You can also click this link for access to the updates. The Henry-Senachwine Board of Education will continue to meet monthly and welcomes public attendance at the meetings.